Upcoming Work
Work has begun on the installation of a 750mm/600mm sanitary mainline along Ontario Street, starting at Greenlane and moving south towards King Street. The alignment of the new sanitary sewer is primarily on the centre and east side of Ontario Street. For the safety of both construction workers and drivers, traffic control measures will be in place, with one lane open during working hours.
Project Timeline (Tentative & Weather-Dependent) | |
Greenlane to Friesen | Beginning to late fall 2024 |
Friesen Intersection Work | Early November 2024 (approximately 5 days) |
Friesen to John | Mid-November to late November 2024 |
John Street Intersection Work | Late November to early December 2024 (approximately 5 days) |
John to King | Early December to late January 2025 |
Restorations & Expected Project Completion | Spring 2025 |
Anticipated Road Closures
- John Street and Ontario Street
- King Street and Ontario Street
Important Notes:
- Business access will remain open throughout the project duration.
- If an access is required to be blocked, the contractor will provide notification.
- Please expect traffic delays while traveling along Ontario Street.
- Side street road closures may occur.
- Night work may be required during the project to minimize daytime disruptions.
- All timelines are subject to change based on site conditions and weather.