Sean Jackson, PMP, C.Tech., Project Manager
David Warden, Manager of Public & Open Spaces
Matt Bruder, MCIP, RPP, Associate Director of Planning and Development
Walter Neubauer, CET, Manager – Technical Services
Sarah Ane - Associate Director, Recreation and Culture
Jessica Wilson – Cultural Development Coordinator
Jasmine Proteau – Acting Cultural Development Coordinator
Olivia Rozema – Cultural Events Program Administrator
Stephanie Bellisimo – Collections Curator
Beth Labrie – Cultural Interpreter
Consultants:
Paul Sapounzi, Lead Partner, +VG The Ventin Group Architects
Travis Forrest, Associate Partner, Project Manager, +VG The Ventin Group Architect
Project Overview
Construction of a new single-story museum and cultural centre approximately 8,400 total gross sq. ft. on the site of the old museum with renewed pedestrian access across the historic site to the Twenty Mile Creek. Full details are available in the project background.
Project Milestones & Progress
Fencing around the site reconfiguredcompleted
Completion date: August 20, 2019
Site preparations and clearingcompleted
Completion date: August 22, 2019
Construction trailer onsitecompleted
Completion date: August 22, 2019
Water & sewer connectionscompleted
Completion date: September 10, 2019
Site excavation for the footings and foundationcompleted
Completion date: September 30, 2019
Footings and foundationcompleted
Completion date: October 2019
Underground hydro connections by NPEIcompleted
Completion date: November 2019
Main floor core slab installedcompleted
Completion date: November 2019
Framing of exterior wallscompleted
Completion date: January 10, 2020
Exterior walls, structural steel roof & windowscompleted
Completion date: February 2020
Masonry work on main floor & elevator shaftcompleted
Completion date: February 2020
Installation of roof truss & deckcompleted
Completion date: February 2020
Exterior wall sheathingcompleted
Completion date: February 2020
Roof membranecompleted
Completion date: March 2020
Exterior spray foam insulationcompleted
Completion date: May 2020
Interior wall framingcompleted
Completion date: August 2020
Mechanical rough incompleted
Completion date: September 2020
Electrical rough incompleted
Completion date: September 2020
Drywallcompleted
Completion date: September 2020
Window installationcompleted
Completion date: September 2020
Paintingcompleted
Completion date: October 2020
Wood ceilingcompleted
Completion date: October 2020
Exterior claddingcompleted
Completion date: December 2020
Main level floorcompleted
Completion date: December 2020
Exterior doorscompleted
Completion date: December 2020
Niagara Peninsula Energy Inc. connectioncompleted
Completion date: December 2020
Commissioning of the HVAC systemcompleted
Completion date: December 2020
Commissioning of the lighting systemcompleted
Completion date: December 2020
Interior doors and hardwarecompleted
Completion date: January 2021
Mechanical finishescompleted
Completion date: January 2021
Electrical finishescompleted
Completion date: January 2021
Millworkcompleted
Completion date: February 2021
Bathroom workcompleted
Completion date: March 2021
Carpeting and baseboardcompleted
Completion date: January 2021
Paintingcompleted
Completion date: January 2021
Elevator delivered and installation begins
Target completion date: April 2021
Elevator installation
Target completion date: April 2021
TSSA approval
Target completion date: April 2021
Building inspections and occupancy permit issued
Target completion date: April 2021
Substantial completion
Target completion date: April 2021
Deficiencies to be completed
Target completion date: April 2021
High density storage system install
Target completion date: May 2021
Installation of opening exhibit
Target completion date: May 2021
Contact Information:
Sean Jackson, Project Manager, email or call 905-563-2799 ext. 258