Frost Road Bridge

Frost Road Bridge Replacement (140m north of Spring Creek Road)

Project Update

Based on the results of the Public Information Centre, the project team is prepared to move forward with completing the design. However, the project will be paused at the 90% design stage of the project and will be finalized in the year of construction which is currently scheduled in the Town’s capital plan for 2031, subject to Council approval.

Please continue to check in with this page for further updates.

Project Timeline

RFP Design AwardCompleted October 2022
30% to 90% Design ReviewCompleted January 2023 - November 2023
Public Information CentreDecember 2023 - January 2024
100% Design and Request for Tender ProcessTBD
Construction Start DateTBD