Project Update
The Durham Road Reconstruction Project is nearing completion, with only final wrap-up activities remaining. As the project winds down, a one-year maintenance period will soon begin to ensure all infrastructure elements meet quality standards and address any potential issues. Thank you for your patience and support throughout this initiative to improve our community’s infrastructure.
Project Timeline | |
Site Investigation and Topographic Survey | Completed |
Design Review | August 2022 - October 2022 |
Public Information Centre | December 2022 |
Design Review | March 2023 - October 2023 |
Request for Tender Process | January 2024 - February 2024 |
Construction | June 2024 - October 2024 |
Maintenance Period | TBD |
Project Information
Questions?
If you have any questions about this project, please contact the project manager:
- Rob Andrea
- Project Manager, Capital Projects